Pet Clinic Equipment Checklist: A 90-Day Pre-Opening Plan for New Veterinary Facilities

A pet clinic equipment checklist is a sequencing tool before it is a shopping list. Because opening a pet clinic equipment timeline is set by lead times and site services rather than by budget alone, the plan below divides the last ninety days into four phases and names what has to be confirmed in each one. It also shows how to equip a new veterinary clinic without ordering devices the building cannot support.

Start the Pet Clinic Equipment Checklist with the Building

Before a model is chosen, confirm what the building can supply: electrical capacity at each position, water and drainage in the preparation room, floor loading and door widths. In a new veterinary clinic these constraints disqualify more equipment than price does, and they are cheapest to resolve while the space is empty.

The Two-Week Site Survey Before Any Order

Collect the documents first: the electrical panel schedule, water pressure and drainage points, room dimensions, and the narrowest doorway on the delivery route. Note where each unit will stand, because a 17 kg oxygen concentrator and a 7.5 kg warming device both need floor positions rather than shelf space. Check the result against your planned room-by-room equipment layout.

Days 90 to 60: How to Equip a New Veterinary Clinic with Long-Lead Items

Order the long-lead items first, because their path from purchase order to running equipment is the longest: imaging, sterilisation and the oxygen supply. Monitors and syringe pumps can follow later, since they need only bench space and a power outlet. Agree delivery dates in writing and book commissioning slots behind them.

What to Confirm on the Monitoring and Infusion Order

For monitoring, match parameters to the station before comparing models. The VE15 monitor publishes a 15-inch colour display with optional CO2 and IBP expansion; the VM12 monitor publishes a 12.1-inch display, three operating modes and under 4 kg with battery. The VSP1 syringe pump publishes 10 to 50 mL syringe sizes and a 0.1 to 1500 mL/h range.

Days 60 to 30: Warming, Sterilisation and Oxygen Supply

The second phase covers the devices that set surgical throughput: forced-air warming, bench-top sterilisation and a delivered oxygen source. These are the items that slip most often, because they need bench space, water or drainage, or dedicated circuit capacity that is only discovered after delivery. Confirm the services before the purchase order is released.

Published Specifications for a Core New-Clinic Set

The table below lists the core set held in this pet hospital equipment and consumables category with the parameters published on this site. Where a value is not published it is marked for confirmation rather than estimated, because supply voltage, circuit capacity and service connections are site decisions rather than catalogue facts.

Product Type Model or Variant Published Specification Power & Supply Site Requirement to Confirm
Multi-parameter patient monitor VE15 15-inch colour LCD; ECG, SpO2, NIBP, RESP, TEMP, HR, PR; optional CO2 and IBP expansion; 15-hour data storage 100-240 VAC, 50/60 Hz, maximum input power 70VA; fuse F2AL 250V; 2Ah 12V rechargeable lithium battery Trolley or wall-mount position and optional recorder to be confirmed per specification
Multi-parameter patient monitor VM12 12.1-inch LCD; diagnostic, monitoring and surgical modes; under 4 kg with battery; mirror display mode AC/DC dual use; 2Ah 12V rechargeable lithium battery; published AC input rating to be confirmed per specification Bench or cart position and optional built-in printer to be confirmed per specification
Syringe (infusion) pump VSP1 10 mL, 20 mL, 30 mL and 50 mL syringes; 0.1-1500 mL/h; 3.2-inch screen; 336 × 120 × 140 mm; 2.0 kg 100-240 VAC, 50/60 Hz; 11.1V 2000mAh battery, off-state charging over 10 hours Pole or rail clamp position to be confirmed per specification
Forced-air warming device VHB 35.0-43.0 °C setting; accuracy ≤±1 °C; 2-minute warm-up; 260 × 295 × 395 mm; 7.5 kg AC 220V, 50Hz/60Hz; power consumption 1500VA Circuit capacity at the surgical position and hose storage to be confirmed with the site electrician
Bench-top steam sterilizer 12 L / 16 L / 18 L / 23 L models Chamber 12-23 L; Ø200 × 354 mm to Ø247 × 448 mm; unit 630 × 442 × 400 mm or 720 × 442 × 400 mm Rated power 1800VA / 2300VA depending on model; supply voltage to be confirmed per specification Water supply, drainage and bench load rating to be confirmed per specification
Oxygen concentrator V-Y501W Oxygen concentration 90%-96%; 36 × 30.5 × 58.5 cm; 17 kg; 250 mL humidifying cup Power cord supplied; published input rating to be confirmed per specification Castor clearance and ventilation space to be confirmed per specification

The heating and sterilisation items are the most sensitive to site services. The forced-air warming device publishes 1500VA at AC 220V, the bench-top steam sterilizer publishes 1800VA or 2300VA by model, and the oxygen concentrator publishes 90%-96% concentration at 17 kg. Chamber volume only turns into throughput once the instrument packs and the cycle schedule are planned, which this guide to veterinary surgical instrument reprocessing sets out.

Days 30 to 0: Commissioning, Acceptance and Dry Runs

Acceptance testing means running each device against its published specification before final payment: warm-up time, infusion accuracy at two rates, a completed sterilisation cycle and measured oxygen concentration. Then hold two dry-run days with the whole team, including one simulated emergency, so the first real patient is not the first time the equipment is used.

An Acceptance Record Worth Keeping

Record the serial number, delivery date, the published value you tested and the measured result, who carried out the test, and the warranty start date. That single page becomes the baseline for every later service visit and calibration check, and it settles any dispute about a unit that arrived outside specification. Keep it with the maintenance and replacement plan.

The First 30 Days: Reading the Pet Clinic Equipment Checklist Against Real Cases

Once the clinic is open, the checklist becomes evidence. Track which devices were used every day, which ones sat idle, and which created a changeover delay. Count starter consumables, filters and wear parts at day thirty and reorder against measured use rather than the original estimate.

Starter Consumables and the First Service Interval

Count what runs out fastest: warming hoses and blankets, syringe sets for 10 to 50 mL pumps, oxygen inlet filter cotton and printer paper. Book the first service visit after thirty days of cases rather than six months after delivery, and use the count to set reorder points. The budget and buying order guide covers how to phase the spending.

Frequently Asked Questions

These are the questions clinic owners, practice managers and distributors raise most often at the start of a fit-out. Each answer stays with what is documented on this site, and anything site-specific is flagged for confirmation with the supplier and the building contractor before an order is released.

How far ahead should a new clinic order its equipment?

Long-lead items are usually ordered around ninety days before opening, with monitors, infusion devices and bench equipment following thirty to sixty days later. The dates that matter are the ones agreed in writing, because shipping and customs sit outside your control.

What should be verified before a device is accepted and paid for?

Run it against the published specification, not against how it looks. Warm-up time, infusion accuracy, a completed sterilisation cycle and oxygen concentration are all checkable in an afternoon. Record the measured values beside the published ones and raise any gap before payment clears.

What is the most common planning mistake in a new fit-out?

Ordering from the catalogue before surveying the building. Devices that need drainage, circuit capacity or a wider doorway tend to be discovered late, and the delay is measured in weeks. The survey takes two weeks and prevents most of it.

Does the same checklist work for an extension or a second site?

Yes, with one change. For a second site, list the items you intend to standardise across locations first, so consumables, training and spare parts stay interchangeable. Site-specific items come second, and only where the new building genuinely requires them.

Request a Quote

Send us the room list, the services available at each position and the opening date you are working to. We will return a phased supply plan with the published specifications for each item, flag the parameters that still need confirmation, and quote in export quantities for clinics, distributors and contractors.

For adjacent planning, see our guides to a camera feeder feeding record and to mobile veterinary equipment for house-call practice. The wider pet supplies range holds the feeding, watering and accessory items that complete a new facility.